Assessment for Sugarcane factory to expand capacity 6000 tcd to 8000 tcd
2017
Member Team
PTPN XII
Feasibility study Palm Oil Mill Biogas Power plant for Sei Buatan and Lubuk Dalam Palm Oil Mill
2015
Member Team
PTPN V
6 sugarcane mill PTPN XI, in area improvement for expand capacity, Energy saving and Product quality
2016
Member Team
PTPN XI
Feasibility Study for Palm Oil Biomass (EFB) Power Plant 11 MW in Tandun cluster (PKS Sei Intan, Sei Rokan, Tandun, Tapung, Terantam) PTPN V Riau .
2015
Team Leader
PTPN V
Feasibility Study for Biogas Power plant 1 MW in Sei Intan and 1,5 MW in Sei Rokan.
2015
Team Leader
PTPN V
Owner Consultant for : Term Of Reference BOT contract, BOT Promoter qualification and selection for Biogas Power Plant Sei Galuh and Sei Garo @ 1 MW
2014
Team Leader
PTPN V
Gap Utilities Analysis of 12 Palm Oil Mill in PT Perkebunan Nusantara V, Riau.
2013
Member Team
PTPN V
Business Analysis for Crushing Plant andesite stone for Rolas Nusantara Tambang
2012
Member Team
PTPN V